Do you have an estimated timeline for when field testing and reengineering [sic] will be complete?

Last post 12-18-2008 9:56 by Julia Austin. 0 replies.
Page 1 of 1 (1 items)
Sort Posts: Previous Next
  • 12-18-2008 9:56

    Do you have an estimated timeline for when field testing and reengineering [sic] will be complete?

    Q: Do you have an estimated timeline for when field testing and reengineering [sic] will be complete?


    A: We can’t provide specific timelines. Our validation criteria require that we collect data from 50 pairs of anemometers for eight weeks. Only when we have sufficient data, and consensus that the sensors are performing up to pre-2006 standards, will we form conclusions and move ahead. There is a short amount of time on either side of those eight weeks to complete engineering activities, deploy sensors, and ramp up manufacturing.

    Filed under: ,