Julia Austin Posted April 6, 2011 Report Share Posted April 6, 2011 The PV power supply is designed to be mounted to the weather-proof pallet used to ship the integrated lighting system. An analysis of soil stability is an essential part of the pre-installation site assessment. Please review Appendix B of the 80m XHD Manual for an explanation of anchor selection and soil assessment. If you are installing on solid ground, a concrete base for the power supply system is not necessary. If you are installing in muddy or damp conditions, it?s possible to pour a concrete pad, but keep in mind that these conditions may also pose a challenge in anchoring the tower. Link to comment Share on other sites More sharing options...